1. What is a project?(項目的定義)
A project is ‘an undertaking that has a beginning and an end and is carried out to meet established goals within cost, schedule and quality objectives’.
Resources are the money, facilities, supplies, services and people allocated to the project.
In general, the work which organisations undertake involves either operations or projects.
2. The Nature of Project Management (項目管理的特性)
Compared with the management of day-to-day operations, project management has the following additional challenges:
·Project teams usually include people from different departments, with different working cultures, who have to work together on the project objectives.
·The work of a project is usually performed once only, unlike operations in which the same tasks may be performed regularly. The project team will, therefore, be dealing with new challenges for the first time.
·The objectives of a project need to be specified, otherwise there may be "scope creep".
·Projects usually have a deadline and a budget.
3. Project Challenges for Management(管理項目的方式)
Project Management Triangle
Each project has key attributes of scope, schedule and cost. These attributes have been coined "the iron triangle" or "triple constraint" because changing any of these will change the effectiveness (i.e. "quality") of the project deliverable.
·Scope—What the project was designed to achieve, either through a business case or through a less formal process. Although usually determined at the beginning of the project, scope may change over time (i.e. "scope creep").
·Schedule
·Cost
The triple constraint illustrates opportunity costs if quality is to be maintained:
·Increasing the scope will require more time, increased cost or both;
·Squeezing the schedule will require narrowing the scope, increasing the cost or both; and
·Decreasing the cost will require narrowing the scope, increasing the time, or both.
Project managers retain responsibility for communicating project management constraints at the outset, monitoring progress as the project matures and communicating variance from plan to the appropriate responsible person:
·Stakeholders often lobby for greater project scope without full awareness of the costs and time that may be required;
·Financial managers or those with budget authority will often lobby for lower costs without being aware of the effects on quality; and
·Department heads that grant resources to the project will frequently lobby for less staff time spent on the project and away from their regular jobs.
Copyright © 2000 - www.electedteal.com All Rights Reserved. 北京正保會計科技有限公司 版權所有
京B2-20200959 京ICP備20012371號-7 出版物經營許可證 京公網安備 11010802044457號
套餐D大額券
¥
去使用 主站蜘蛛池模板: 久久成人在线 | 欧美一区二区三区视频在线观看 | 亚洲综合国产一区二区三区 | 国产精品一区一区 | 色婷婷中文 | 国产高清视频 | 国产福利视频 | 久久久亚洲一区 | 久久wwww| 国产成人综合在线 | 亚洲一区二区精品视频 | av影片在线| 国产精品美女久久久久久久网站 | 欧美性区 | 精品香蕉视频 | 精品久久久精品 | 日本久久久一区二区三区 | 亚洲日韩中文字幕一区 | 国内精品国产三级国产在线专 | 综合久久久久久久 | 91黄在线看 | 精品国产一区二区三区四区四 | 国产在线观看一区二区三区 | 亚洲精品乱码久久久久久蜜桃麻豆 | 午夜精品久久久久久99热软件 | 亚洲成人一区二区在线 | 国产乱码精品 | 波多野结衣国产 | 久久久亚洲一区 | 亚洲免费在线观看视频 | 日韩欧美精品一区二区三区经典 | 久久国产亚洲精品 | 日本不卡中文字幕 | 亚洲一区二区三区久久 | 999久久精品 | 91精品福利 | 一区二区网站 | 亚洲欧美日韩国产综合 | 黄色激情视频在线观看 | 深夜影院深a | 亚洲乱码国产乱码精品精 |