ACCA P5考試:Software Supplier Selection
1. Software Supplier Selection
Ideally, this process will revolve around the Invitation to Tender (ITT), which has set out the firm's functional, technical and contractual requirements such that the project team can compare competing solutions. The ITT may also be known as a Request for Proposal (RFP).
Skidmore and Eva suggest a five-stage process for vendor selection.
1.1. Obtaining tenders: The ITT will typically be sent to several companies with capability to deliver the system change and will include sections that describe the response process, the response format and key dates. In addition, the ITT will have the following sections:
Background
Summary of current IT system(s)
Key functional requirements
Key technical requirements
Price considerations
Request for references
1.2. First-pass selection: For common, off-the-shelf systems, there may be many vendors that can supply the software. The first pass allows the selection committee to identify three to six suppliers that specify the best software solution, implementation process and value for money.
Generate a worksheet documenting responses to key points in the ITT.
Sort the worksheet based on these responses.
Screen down to a number of vendors that the committee can further explore.
1.3. Second-pass selection: The selection committee does an indepth review of firms surviving the first pass.
Schedule and hold supplier presentations.
Contact references provided in the ITT process.
For larger or more complicated projects, it may be necessary for the IT team to assess the supplier
Determine each supplier's financial stability.
Select two to three of the most promising suppliers.
Conduct site visits where the software has been implemented.
Decide on a vendor.
1.4. Implementation: This will include all steps required to
realise the key success criteria:
equipment installation (if necessary);
software installation and time frames;
software customisation and response times; and
training.
1.5. Managing the long-term relationship: This part of the selection process should be specified to some extent during the second-pass selection stage, and finalised prior to actually negotiating and signing the final contract. This will involve the steps in virtually any relationship, including:
developing (and limiting) expectations on both sides;
establishing channels of communication; and
establishing key dates and reminding the supplier of key dates at various points through implementation, update, upgrade and all other points in the cycle.
歷年樣卷
考試大綱
詞匯表
報(bào)考指南
考官文章
思維導(dǎo)圖
安卓版本:8.8.0 蘋果版本:8.8.0
開發(fā)者:北京正保會計(jì)科技有限公司
應(yīng)用涉及權(quán)限:查看權(quán)限>
APP隱私政策:查看政策>
HD版本上線:點(diǎn)擊下載>
官方公眾號
微信掃一掃
官方視頻號
微信掃一掃
官方抖音號
抖音掃一掃
Copyright © 2000 - www.electedteal.com All Rights Reserved. 北京正保會計(jì)科技有限公司 版權(quán)所有
京B2-20200959 京ICP備20012371號-7 出版物經(jīng)營許可證 京公網(wǎng)安備 11010802044457號
套餐D大額券
¥
去使用 主站蜘蛛池模板: 99精品久久久国产一区二区三 | 51ⅴ精品国产91久久久久久 | 国产成人免费在线 | 天天色网站 | 精品一区二区国产 | 99福利| 日韩一区三区 | 91精品国产综合久久精品图片 | 91av超碰 | 日韩中文在线视频 | 成人性生交大片免费看视频r | av在线播放网站 | 国产亚洲欧美一区 | 国产成人精品视频 | 日韩激情一区 | 久久精品国产久精国产 | 亚洲 欧美 变态 国产 另类 | 国产一区二区三区免费 | 亚洲午夜视频在线 | 久久久人 | 在线中文字幕亚洲 | 亚洲午夜久久久久 | 国产精品成人3p一区二区三区 | 免费看亚洲 | 精精国产xxxx视频在线播放 | 视频一区欧美 | av中文字幕第一页 | 成人在线免费网站 | 99国内精品| 欧美精品成人影院 | 青青草国产 | 在线观看成人av | 成人免费一区二区三区视频网站 | 99亚洲精品| 欧美性一级| 99久久久无码国产精品 | 久久久91精品国产 | 精品66| 国产精品系列在线 | 日韩免费高清视频 | 成年人视频在线免费观看 |